WHITE PLAINS, N.Y. -- A tentative schedule has been set by the New York State Department of Transportation and their contractor for remaining road work on Rte. 22 and White Plains Rd. 

NYSDOT has announced a tentative schedule for road repairs.

NYSDOT has announced a tentative schedule for road repairs.

Photo Credit: Facebook

NYSDOT's remaining schedule is as follows:

  • Nov. 4 through 6 - milling and top course work paving from Crest to Wimot (will progress as a moving operation)
  • Nov. 8 through Nov. 12 - milling and top course paving to begin and end from Wilmot to Sprague (will progress as a moving operation)
  • TBD - traffic signal loop work at the intersections and permanent striping will be installed after completion of the top course paving and loops, respectively.

All work is scheduled for nighttime. 